A Willowpeak Capital Group guide to the City of Williston, North Dakota zoning map, planning and zoning process and building permits, written for owners timing a build-out or a lease.
Reading the Williston, ND Zoning Ordinance Before Leasing Space for a Chiropractic Clinic
The City of Williston, ND zoning ordinance is Ordinance No. 613, as amended; the Planning and Zoning department publishes it, the subdivision ordinance and a list of amendments on its zoning ordinances page. One amendment listed there, Ordinance No. 884, allows a special permitted use for professional offices to operate in already existing structures in certain districts.
A chiropractic clinic looking at space in an existing building should read the district rules for that parcel and ask Planning and Zoning whether a clinic is allowed outright, by special use, or not at all, before signing the lease.
Williston, ND Planning and Zoning: Zones to Check Before a Restaurant Signs a Lease
The city publishes a city zoning map as a PDF and an interactive city map. District names in the ordinance amendments include C-3 Restricted Commercial, M-2 Heavy Industrial and a P-2 Planned Unit Development overlay. A restaurant should check the parcel's district, parking and sign rules before committing to a lease.
Planning and Zoning oversees land use within the city limits and a one-mile extraterritorial area, and administers the comprehensive plan, the zoning ordinance, the subdivision ordinance and the Renaissance Zone downtown, according to the department.
Williston, ND Building Department Before Technician Payroll at an Auto Repair Shop
Building Safety, in the City of Williston Center for Development, issues building permits. Its FAQ says permits are required for any new construction, addition, remodeling project or structural alteration, and for mechanical and plumbing projects; finish work such as cabinets or painting does not need one.
An auto repair shop adding a lift that needs new concrete, or rewiring a bay, should ask Building Safety whether the work needs a permit before hiring technicians around the opening date.
The FAQ lists what a permit application needs: the address and legal description of the property, the intended use, the estimated cost of construction, and a site plan showing existing buildings and the proposed project. The estimated cost on the permit and the bid in the funding request should match, since a partner may compare them. The FAQ also advises owners to check that a hired contractor holds a current North Dakota contractor license, through the Secretary of State's contractor lookup.
City of Williston, ND Building Permits: Timing a Contractor Remodel Around Plan Review
Since January 1, 2025, the city requires plans for commercial projects to be drawn to scale and applications to be complete, with all required drawings, at submittal; incomplete applications are rejected, according to the building permit applications page. The page lists separate applications for commercial building, commercial alteration, demolition, signs, site grading and temporary use.
The Building Safety FAQ says a permit generally takes less than one hour depending on the project, with at least 3 weeks for new homes and garages, and that the permit holder arranges inspections. A contractor timing a remodel should plan around those steps.
Pre-Application Meetings and Commission Dates in Williston, ND
Planning and Zoning requires a pre-application meeting with a planner at least a week before any application, and applications are due the Friday 4 weeks before the Planning and Zoning Commission meeting that will hear the case, according to the department.
The commission meets on the third Monday of each month at 5:30 pm at City Hall, 22 East Broadway, and the Development Review Committee on the first Monday at 1:15 pm at the Center for Development, 113 4th Street East, per the city's commission page. Confirm dates with the city before planning around them.
Where the Permit Timeline Meets the Funding Timeline
A funding partner may want to see that a project can be permitted before it funds it. An owner who has held the pre-application meeting and has a drawn-to-scale plan can show that. A rezoning or special use request adds at least a month to the timeline, and the funding request should allow for it.
By the city's own deadlines, a case that goes to the commission needs at least five weeks before the meeting: the pre-application meeting a week ahead of the application, and the application itself due four weeks before the hearing (our arithmetic). A business license, where one is needed, goes through the Finance Department and then to the City Commission, which meets on the second and fourth Tuesdays, according to the city's license page.
Bring the permit status to the first call. The term loan page covers build-outs, and the restaurant page covers kitchen work.
By Willowpeak Capital Group · Updated